Investor/Analyst Briefing 1H23

Investor/Analyst Briefing 1H23

Choose

1H23

Investor/Analyst Briefing 2023

Financial Highlight

 

  • Strong track record of revenue growth driven by production ramp up of nickel processing facilities.

  • Healthy profitability margin with double digit gross profit, EBITDA and net profit margin.

  • Stagnant growth of performance’s EBITDA andNet profit in 1H YoY was due to the lower of share in net profit associates coming from HPL.

Mining Operations

 

 

  • A strong growth in mining production was in line with the increase in smelter and refinery production capacity.

  • In FY2020, TBP only had 1 operating smelter, MSP, with 4 production lines and production capacity of 25,000 tons contained Ni/year.

  • In FY2021, two lines of HPAL in PT HPL was completed with a capacity of 37,000 tons/year of nickel cobalt compounds.

  • In FY2022 and 1H 2023, the demand increased substantially from the completed 8 production lines 2 in RKEF nickel processing facility of PT HJF with capacity of 95,000 tons contained Ni/year of ferronickel, as of June 2023, 2 production lines are still in ramping up process, and also increased from commissioning of the 3rd line 3 of HPAL in PT HPL.

RKEF Operations

 

 

  • From FY2020 - FY2022, FeNi production was only coming from MSP which has been operating since 2017.

  • The HJF RKEF has commenced its operation at the end of FY2022 with 2 production lines. The next 3 production lines, 3rd, 4th, and 5th lines were completed in January 2023, February 2023 and March 2023, respectively. The remaining 3 production lines completed by end of 1H 2023.

  • HJF is expected to reach full production capacity in Q3 2023. Thus, it drives the significant growth of FeNi Sales in 1H 2023.

HPAL Operations

 

  • At the end of 2021, two MHP production lines of PT HPL have commenced its operation with designed capacity of 37,000 tons contained Ni/year. The first line ramped up to full capacity within 4 months and the second line ramped up only in 2 months. 

  • The third line with designed capacity of 18,000 tons contained Ni/year commissioned in January 2023 and ramped up to full capacity also in 2 months. As per April 2023, the total production capacity MHP has reached 55,000 tons contained Ni/year. 

  • The realization of MHP production in 2022 was exceeded the installed capacity.

  • PT HPL started to produce Nickel Sulfate in April 2023 and did the initial export in June 2023.